Provision of Brick Wall Construction for General Processing Facilities No. 3 in Halfaya CPF3 & Related System Project

Contract No.: CPF3&0609/SBC2017/008
Contract Price: USD 1,284,260.00

Description:

Construction of a 2,375-meter brick perimeter wall for CPF3, including excavation of approximately 3,400 m³, blinding concrete, reinforced concrete works, backfilling, installation of steel fencing and razor wire, cement mortar finishing, painting of both sides of the wall, and all associated civil works.